Over the past year, VMS has conducted value
studies for the following clients:
California
Dept. of Transportation City
of Fontana, CA City
of New York, NY City
of Vancouver, WA
Golden
Gate Bridge District
Santa
Clara Valley Trans. Authority U.S.
Army Corps of Engineers U.S.
Navy
Provided below is a small sample of project VMS, inc. has provided
value study facilitation services for over the past year.
Antlers Bridge Replacement - Lake Shasta, CA
This
project proposes to replace the existing Antlers Bridge, on Interstate 5, which
spans the Sacramento River arm of Lake Shasta. Included in the scope is
consideration to modify the centerline alignment of the freeway to improve radii
of the two curves immediately south of the structure. Depending on the concepts
adopted, the new structure will have two 3.6-meter northbound lanes, three
3.6-meter southbound lanes, a 6.6-meter median, and 3.0-meter shoulders.
The original estimated cost of the project was approximately $105 million.
The VMS led
Value Analysis team developed eleven VA alternatives, six of which were
organized into two sets. Of these alternatives, two were accepted and three
others were identified as conditionally accepted. One of the accepted
alternatives resulted in the adoption of a new highway alignment that will
improve the horizontal geometry and save over $12 million in construction
costs. Another accepted alternative will allow the contractor to develop a
temporary boat ramp for construction purposes on the west side of the north
abutment for staging purposes. These two alternatives resulted in a net
performance improvement of 19% with an increase in total value by 35%.
Inland Empire Transportation Management Center
- Fontana, CA
The
California Department of Transportation’s District 8, encompassing Riverside and
San Bernardino counties, has partnered with two local transportation agencies to
plan and construct a new Transportation Management Center (TMC). Facility design
is currently scheduled to begin in December 2004, with construction starting in
February 2007, and move-in planned for June 2008. This facility will co-locate
the California Highway patrol’s 911 Emergency Response operations with Caltrans
traffic management operations in this facility. The TMC will
consist of a 2-story base isolated structure with a total floor space area of
45,000 square feet. An 80- to 120-foot communications tower will be constructed
on the site for the TMC. A Park and Ride lot of approximately 200 spaces will
be developed as part of the TMC. The TMC would be designed to meet the
requirements of the Essential Services Act of 1986 and will accommodate a staff
of approximately 175 employees, which will be moved from two facilities in the
City of San Bernardino.
The project is currently in the early
stages of design development. The budget for the project per the Project Study
Report, dated September 13, 2001, is approximately $30 million.
The VMS, Inc. led Value Analysis team identified 21
VA alternatives that recommend improvements to all aspects of the design.
The VA alternatives have the potential of saving over $2 million in
construction costs and $5 million in life cycle costs while improving project
performance by nearly 50%.
SR 29 / SR 12 Interchange Improvements, Napa, CA
VMS recently completed a
challenging project for the California Dept. of Transportation. The SR
29/SR 12 Interchange Improvements project is being developed in order to improve
operations and traffic safety at the current junction, which is a signalized,
at-grade intersection. The original Project Study Report identified eight build
alternatives to be further studied during the Project Approval Environmental
Document (PA/ED) phase. The alternatives included three at-grade improvements
(two of which are low cost alternatives), upgrading the intersection to an
interchange with a tight diamond, single point or partial cloverleaf
configuration, including a low cost interchange alternative, and constructing a
flyover for the Route 29 southbound to Route 12 eastbound traffic movement.
The estimated capital costs range from $26 million
for the tight diamond interchange to $42 million for the partial cloverleaf
interchange. This intersection is being studied at the request of the Napa
County Transportation Planning Agency (NCTPA).
The VMS, inc. led Value Analysis team developed
seven alternatives for improvement of the project. One of the most important
alternatives, which has subsequently been identified as the "preferred"
alternative, is a modified single point urban interchange. This alternative
will dramatically improve project performance by approximately 60%.
Another innovative VA alternative would acquire a construction easement south of
the existing alignment in order to construct a temporary facility to maintain
traffic while SR 12 is reconstructed and the new overcrossing is built. This
alternative would significantly improve construction staging, reduce the
construction schedule by half a year, and save $10's of millions in highway-user
costs.
Bowery Bay Water Pollution Control Plant, Queens, NY
The
Bowery Bay Water Pollution Control Plant (WPCP) is located on Berrian Boulevard
in Astoria, Queens, New York. It began operation in 1939 and serves the western
portion of the Borough of Queens. The Bowery Bay WPCP has undergone a
series of expansions and upgrades over the years with major construction
projects occurring in 1940, 1949, 1954, and 1971-75. The plant is currently
undergoing an upgrade which includes new raw sewage pumps, return activated
sludge (RAS) pumps for 100% RAS flow, primary tank skimming equipment,
hypochlorination equipment, and a residuals handling building.
The plant is a step-aeration activated
sludge plant designed for an average dry weather flow of 150 million gallons per
day (mgd). Maximum primary treatment capacity is 300 mgd. Secondary treatment
facilities can handle 225 mgd, which is one and one-half times the average dry
weather flow. The estimated average daily flow for 1990 was 159 mgd and the mean
dry weather flow was 143 mgd. Two intercepting sewers, one low level and one
high level, convey wastewater to the plant. The invert of the low level
interceptor as it enters the plant is at elevation -36.1 feet below the invert
of the high level sewer. Treated effluent is discharged into the Rikers Island
Channel through a 10-foot diameter outfall.
The reconciled cost estimate places the
construction value of the proposed upgrades at approximately $106 million with a
target completion date of December 31, 2010. The original proposed plan was
estimated at $149 million.
The VMS, Inc. led VA Study identified 29
alternatives and 27 design suggestions. Of these, 33 were accepted for a
total of $3.8 million in savings. Four additional alternatives are being
studied further, which could yield an additional $2 million.